Construction of the new northern breakwater at Bunbury’s Casuarina Boat Harbour is now complete to its full extent at low level, marking a major milestone in the delivery of the project.
The 460-metre structure, costing $69.2 million is the centrepiece of the Transforming Bunbury’s Waterfront (TBW) initiative.
The new structure is already providing increased sheltering at the harbour ahead of winter and in parallel, work to reclaim land at the facility is progressing for the future boat lifting and servicing lease sites.
The vision for the harbour will see it house up to 300 future boat pens and become a regional hub for the marine industry.