Work starts on $10.8 million Jetty Rd causeway redevelopment

News for the Department of Transport

07
Nov
2018

Work has commenced on the first phase of the $10.8 million Jetty Road causeway redevelopment at Casuarina Boat Harbour.

Department of Transport Director of Project Delivery Cameron Smith said in the next few weeks contractors would start trucking the 24,000 tonnes of locally sourced rocks to site for placement along the causeway to strengthen the structure.

"Every effort is being made to limit the impact of the work on the surrounding community and harbour users with restrictions on truck movements and continued access to boat pens on the causeway," Mr Smith said.

"Trucks working on the project are only allowed to operate from 7am to 6pm Monday to Friday and will finish at 5pm on Saturday. DoT's on-site supervisor will work closely with the contractor to minimise noise and dust and the truck speed has been capped at 40 kilometres per hour for increased community safety.

"While there's no access to the causeway beyond the jetties for the duration of the project, penholders will have dedicated parking close to the jetties and will be updated on the progress of works."

The project is a key part of Stage 2 of the Transforming Bunbury's Waterfront project.

Mr Smith said the causeway rock refurbishment was expected to be complete by mid-2019, triggering Phase 2 of the project which will see the roadway reconstructed, 164 parking bays created, landscaping and construction of public toilets and other facilities if the budget allows.

Visit www.transport.wa.gov.au/jettyroadcauseway for more information about the project.

Media contact: media@transport.wa.gov.au

Page last updated: Thu Nov 15 2018 1:53:10 PM